CHANNEL SUPPORT FOR FORMING CONCRETE TRENCH DRAIN

Non-Final OA §102
Filed
Mar 28, 2024
Examiner
PATEL, KALPIT CHANDRAKANT
Art Unit
Tech Center
Assignee
Bg-Graspointner Inc.
OA Round
1 (Non-Final)
80%
Grant Probability
Favorable
1-2
OA Rounds
9m
Est. Remaining
99%
With Interview

Examiner Intelligence

Grants 80% — above average
80%
Career Allowance Rate
4 granted / 5 resolved
+20.0% vs TC avg
Strong +25% interview lift
Without
With
+25.0%
Interview Lift
resolved cases with interview
Typical timeline
3y 2m
Avg Prosecution
11 currently pending
Career history
17
Total Applications
across all art units

Statute-Specific Performance

§101
2.6%
-37.4% vs TC avg
§103
48.7%
+8.7% vs TC avg
§102
30.8%
-9.2% vs TC avg
§112
18.0%
-22.0% vs TC avg
Black line = Tech Center average estimate • Based on career data from 5 resolved cases

Office Action

§102
Notice of Pre-AIA or AIA Status The present application, filed on or after March 16, 2013, is being examined under the first inventor to file provisions of the AIA . In the event the determination of the status of the application as subject to AIA 35 U.S.C. 102 and 103 (or as subject to pre-AIA 35 U.S.C. 102 and 103) is incorrect, any correction of the statutory basis (i.e., changing from AIA to pre-AIA ) for the rejection will not be considered a new ground of rejection if the prior art relied upon, and the rationale supporting the rejection, would be the same under either status. Drawings The drawings filed on 03/28/2024 are acceptable subject to correction of the informalities indicated below. In order to avoid abandonment of this application, correction is required in reply to the Office action. The correction will not be held in abeyance. Fig. 2: One of the three elements (18 - Crenelations) on Figure 2 points to an element (20) which is a hook. Appropriate correction is required. Fig. 2: Element (14 - Base) on Figure 2 incorrectly points to the interlocking support (12). Appropriate correction is required. Fig. 2: Element (12 - Interlocking Support) on Figure 2 incorrectly points to the base (14). Appropriate correction is required. Claim Rejections - 35 USC § 102 The following is a quotation of the appropriate paragraphs of 35 U.S.C. 102 that form the basis for the rejections under this section made in this Office action: A person shall be entitled to a patent unless – (a)(1) the claimed invention was patented, described in a printed publication, or in public use, on sale, or otherwise available to the public before the effective filing date of the claimed invention. (a)(2) the claimed invention was described in a patent issued under section 151, or in an application for patent published or deemed published under section 122(b), in which the patent or application, as the case may be, names another inventor and was effectively filed before the effective filing date of the claimed invention. Claim 1 is rejected under 35 U.S.C. 102(a)(1) as being anticipated by Roger L. Toffolon (EP 0057061) herein referred to as Toffolon. Regarding Claim 1: Toffolon teaches (see Figs. 1-4) a multi-part form device for casting structural concrete units. With a pair of supports, each of which has a base (60-vertical surfaces & 62-horizontal bracing members) supporting a pair of latches (56-vertical surface) extending therefrom, wherein each of the pair of latches includes crenelations (see annotated figure below) on a plurality of supports (element 62-bracing members & 56-vertical surface) at the end of which a hook (elements 58-sidewall end surface & 54-sidewall form members) is disposed of. Toffolon further teaches wherein each of the pair of supports further includes a strut (element 26-base and support means) extending between the pair of latches (56-vertical surface); and wherein the base includes a boss (element 110-lugs) formed therethrough with a through-bore (elements 106/108-lugs) that are dimensioned to accommodate a rod of rebar (element 100-guideways). Examiner notes that this is a broader interpretation of the structures than those disclosed in the instant specification, however, it is noted that the claims do not include any explicit recitations regarding the structural nature of the elements in the same detail. As such, it is noted that a more explicit recitation of the engagement between the crenelations and the latch members in keeping with the instant specification would likely overcome the provided rejection. PNG media_image1.png 528 730 media_image1.png Greyscale Conclusion Any inquiry concerning this communication or earlier communications from the examiner should be directed to KALPIT C. PATEL whose telephone number is (571)272-3053. The examiner can normally be reached 7.30am to 5pm. Examiner interviews are available via telephone, in-person, and video conferencing using a USPTO supplied web-based collaboration tool. To schedule an interview, applicant is encouraged to use the USPTO Automated Interview Request (AIR) at http://www.uspto.gov/interviewpractice. If attempts to reach the examiner by telephone are unsuccessful, the examiner’s supervisor, Christopher Sebesta can be reached at (571) 272-0547. The fax phone number for the organization where this application or proceeding is assigned is 571-273-8300. Information regarding the status of published or unpublished applications may be obtained from Patent Center. Unpublished application information in Patent Center is available to registered users. To file and manage patent submissions in Patent Center, visit: https://patentcenter.uspto.gov. Visit https://www.uspto.gov/patents/apply/patent-center for more information about Patent Center and https://www.uspto.gov/patents/docx for information about filing in DOCX format. For additional questions, contact the Electronic Business Center (EBC) at 866-217-9197 (toll-free). If you would like assistance from a USPTO Customer Service Representative, call 800-786-9199 (IN USA OR CANADA) or 571-272-1000. /KALPIT CHANDRAKANT PATEL/Examiner, Art Unit 3671 /CHRISTOPHER J SEBESTA/Supervisory Patent Examiner, Art Unit 3671
Read full office action

Prosecution Timeline

Mar 28, 2024
Application Filed
Aug 17, 2026
Non-Final Rejection mailed — §102 (current)

Precedent Cases

Applications granted by this same examiner with similar technology

Patent 12698609
WHEEL ASSEMBLY FOR A SOIL COMPACTOR
3y 4m to grant Granted Aug 04, 2026
Study what changed to get past this examiner. Based on 1 most recent grants.

Strategy Recommendation AI-generated — please review before filing

Get a prosecution strategy drawn from examiner precedents, rejection analysis, and claim mapping.
Typically takes 5-10 seconds — AI-generated, attorney review required before filing

Prosecution Projections

1-2
Expected OA Rounds
80%
Grant Probability
99%
With Interview (+25.0%)
3y 2m (~9m remaining)
Median Time to Grant
Low
PTA Risk
Based on 5 resolved cases by this examiner. Grant probability derived from career allowance rate.

Sign in with your work email

Enter your email to receive a magic link. No password needed.

Personal email addresses (Gmail, Yahoo, etc.) are not accepted.

Free tier: 3 strategy analyses per month