Notice of Pre-AIA or AIA Status
The present application, filed on or after March 16, 2013, is being examined under the first inventor to file provisions of the AIA .
Information Disclosure Statement
No Information Disclosure Statement was submitted.
Claim Rejections - 35 USC § 112
The following is a quotation of 35 U.S.C. 112(b):
(b) CONCLUSION.—The specification shall conclude with one or more claims particularly pointing out and distinctly claiming the subject matter which the inventor or a joint inventor regards as the invention.
The following is a quotation of 35 U.S.C. 112 (pre-AIA ), second paragraph:
The specification shall conclude with one or more claims particularly pointing out and distinctly claiming the subject matter which the applicant regards as his invention.
Claims 2, 6, 7, 10, rejected under 35 U.S.C. 112(b) or 35 U.S.C. 112 (pre-AIA ), second paragraph, as being indefinite for failing to particularly point out and distinctly claim the subject matter which the inventor or a joint inventor (or for applications subject to pre-AIA 35 U.S.C. 112, the applicant), regards as the invention.
Claim 2 recites the limitation "the first workload" in lines 2-5 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the first workload” should instead be “the first computing workload”. Further, claim 2 recites the limitation “the second workload” in lines 6-8 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the second workload” should instead be “the second computing workload”.
Claim 6 recites the limitation "the first " in line 2 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the first running computing workload” should instead be “the first computing workload”.
Claim 7 recites the limitation "the " in line 2 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the ” should instead be “the ”. Further, claim 7 recites the limitation "the first" in line 3 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the first workload” should instead be “the first computing workload”.
Claim 10 recites the limitation "the " in lines 2-3, and 5 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the ” should instead be “the ”.
Claim 12 recites the limitation "the " in line 3 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the ” should instead be “the ”.
Claim 14 recites the limitation "the" in line 4 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the” should instead be “a”. Further, claim 14 recites the limitation "the plurality of running workloads" in line 10 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the plurality of running workloads” should instead be “the plurality of running computing workloads”.
Claim 19 recites the limitation "the" in lines 2-5 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the” should instead be “the first accelerator resource”.
Claim 20 recites the limitation "the" in line 2 of the claim. There is insufficient antecedent basis for this limitation in the claim. For examination purposes the examiner has assumed that “the” should instead be “one or more processors”.
Claim Rejections - 35 USC § 101
35 U.S.C. 101 reads as follows:
Whoever invents or discovers any new and useful process, machine, manufacture, or composition of matter, or any new and useful improvement thereof, may obtain a patent therefor, subject to the conditions and requirements of this title.
Claims 1-20 are rejected under 35 U.S.C 101 as being directed to an abstract idea without significantly more.
Claim 1,
Per Step 1: Claim 1 is directed to “A computing device, comprising: one or more processors; and one or more non-transitory computer-readable storage media storing programming for execution by the one or more processors, the programming comprising instructions to: […]” which is directed to one of the four statutory categories
Per Step 2A, Prong 1: Claim 1 recites the limitations:
monitor use of a first accelerator resource allocated to a first computing workload;
determine, based on monitoring the use of the first accelerator resource allocated to the first computing workload, that the use of the first accelerator resource allocated to the first computing workload satisfies an idleness condition; and
reallocate, based at least on determining that the use of the first accelerator resource allocated to the first computing workload satisfies the idleness condition, […]resource to a second computing workload, the second computing workload being a pending computing workload;
All of which can be performed in the human mind through observation, evaluation, judgement and opinion, with the aid of pen and paper, and therefore are reciting a mental process.
Accordingly, claim 1 recites a judicial exception (i.e. abstract idea).
Per Step 2A, Prong 2:
The additional elements recited in claim 1 include:
A computing device, comprising: one or more processors;
and one or more non-transitory computer-readable storage media storing programming for execution by the one or more processors, the programming comprising instructions to:
Regarding limitation (i), the limitation recites generic computer components such that the mental process, i.e. judicial exception, is performed on a generic computer which is not indicative of integration into a practical application. See MPEP 2106.04(a)
Regarding limitation (ii), the limitation recites generic computer components such that the mental process, i.e. judicial exception, is performed on a generic computer which is not indicative of integration into a practical application. See MPEP 2106.04(a)
Per Step 2B:
Regarding the additional element (i) the limitation is reciting generic computer components to perform the steps, which can be performed in the human mind, not indicative of integration into a practical application. The courts have found simply requiring the generic computer components to perform generic computer function is well understood routine and conventional. See MPEP 2106.05(d) and 2106.05(f)
Regarding the additional element (ii) the limitation is reciting generic computer components perform the steps, which can be performed in the human mind, not indicative of integration into a practical application. The courts have found simply requiring the generic computer components to perform generic computer function is well understood routine and conventional. See MPEP 2106.05(d) and 2106.05(f)
The combination of these additional elements amount to a method comprising steps which can be performed mentally and are implemented by generic computer functions with mere instructions to apply the abstract idea on a computer.
Therefore, the additional elements, which considered individually and in combination, fail to add an inventive concept to the claim.
Consequently, claim 1 as a whole does not amount to significantly more than the recited judicial exceptions and the claim is not eligible.
Claim 2 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 2 recites,
the first workload comprises first workload information that comprises: a category associated with the first workload; a priority associated with the first workload; and a start time associated with the first workload;
and the second workload comprises second workload information that comprises: a category associated with the second workload; and a priority associated with the second workload.
Regarding additional limitation element (i), the element further limits the first workload to have the specified information that is a component of judicial exceptions from claim 1 and can therefore be performed in the human mind through observation, evaluation, judgement, and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
Regarding additional limitation element (ii), the element further limits the second workload to have the specified information that is a component of judicial exceptions from claim 1 and can therefore be performed in the human mind through observation, evaluation, judgement, and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
Claim 2 does not recite any additional elements beyond those recited in claim 1.
Accordingly, for the same reasons presented in claim 1, the additional elements are not indicative of integration into a practical application, nor do they amount to significantly more than the recited judicial exceptions. Thus, claim 2 is not eligible.
Claim 3 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 3 recites,
determine that the use of the first accelerator resource does not satisfy an idleness threshold which can be performed in the human mind through observation, evaluation, judgement and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
Accordingly, for the same reasons presented in claim 1, the additional elements are not indicative of integration into a practical application, nor do they amount to significantly more than the recited judicial elements. Thus, claim 3 is not eligible.
Claim 4 is dependent on claim 3, and therefore inherits the same judicial exceptions recited in claim 3.
Further claim 4 recites,
determine, according to the accelerator usage information, whether average accelerator usage over a time period satisfies an idleness threshold; and
determine, based at least on determining that the average accelerator usage over a time period does not satisfy the idleness threshold, that the use of the first accelerator resource allocated to the first computing workload satisfies an idleness condition both of which can be performed in the human mind through, observation, evaluation, judgement and opinion, with the aid of pen and paper, and are therefore reciting a mental processes.
The additional elements of claim 4 include:
access accelerator usage information for the first accelerator resource;
Per Step 2A and 2B:
The additional element (i) recited amounts to mere data gathering steps which is found to be insignificant extra-solution as it is merely gathering data prior to and for use by the judicial exception, which is not indicative or integration into a practical application. Further, the additional element (i) is retrieving information in over a network which is well-understood, routine, and conventional activity. See MPEP 2106.05(d). The courts have found adding extra-solution activity and well-understood, routine, and conventional activity is not enough to amount to significantly more than the recited judicial exception. See MPEP 2106.05(a, g).
Therefore, the additional elements amount insignificant extra solution activity which when considered individually and in combination with claim 3, fail to add an inventive concept to the claim and do not amount to significantly more than the judicial exceptions. Therefore claim 4 is ineligible.
Claim 5 is dependent on claim 4, and therefore inherits the same judicial exceptions recited in claim 3.
Further claim 5 recites,
wherein the idleness threshold is zero
which further limits the judicial exception of claim 4 to have a specific value when performing the mental process and can therefore be performed in the human mind through observation, evaluation, judgement, and opinion, with the aid of pen and paper, and are therefore in combination recites a mental process.
Claim 5 does not recite any additional elements beyond those recited in claim 4.
Accordingly, for the same reasons presented in claim 4, the additional elements are not indicative of integration into a practical application, nor do they amount to significantly more than the recited judicial exceptions. Thus, claim 5 is not eligible.
Claim 6 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 6 recites,
receive accelerator usage information from the first accelerator resource.
Step 2A and 2B:
The additional element (i) recited amounts to mere data gathering steps which is found to be insignificant extra-solution as it is merely gathering data prior to and for use by the judicial exception, which is not indicative or integration into a practical application. Further, the additional element (i) is retrieving information over a network which is well-understood, routine, and conventional activity. See MPEP 2106.05(d). The courts have found adding extra-solution activity and well-understood, routine, and conventional activity is not enough to amount to significantly more than the recited judicial exception. See MPEP 2106.05(a, g).
Therefore, the additional elements amount to insignificant extra solution activity which when considered individually and in combination with claim 1, fail to add an inventive concept to the claim and do not amount to significantly more than the judicial exceptions. Therefore claim 6 is ineligible.
Claim 7 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 7 recites,
determine, prior to reallocating the accelerator resource to the second computing workload, that the first workload has been running for a toleration time period which can be performed in the human mind through observation, evaluation, judgement and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
Accordingly, for the same reasons presented in claim 1, the additional elements are not indicative of integration into a practical application, nor do they amount to significantly more than the recited judicial elements. Thus, claim 7 is not eligible.
Claim 8 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 8 recites,
the second computing workload is one of a plurality of pending computing workloads; the element further limits the second workload to have the specified information that is a component of judicial exceptions from claim 1 and can therefore be performed in the human mind through observation, evaluation, judgement, and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
determine a selected pending workload to be the second computing workload according to respective priorities of the plurality of pending computing workloads which can be performed in the human mind through observation, evaluation, judgement and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
The additional elements of claim 8 include:
access a pending workload queue that comprises the plurality of pending computing workloads;
obtain prioritization information for the plurality of pending computing workloads;
Per Step 2A and 2B
Regarding additional element (i), the element recited amounts to mere data gathering steps which is found to be insignificant extra-solution as it is merely gathering data prior to and for use by the judicial exception, which is not indicative or integration into a practical application. Further, the additional element (i) is retrieving information over a network which is well-understood, routine, and conventional activity. See MPEP 2106.05(d). The courts have found adding extra-solution activity and well-understood, routine, and conventional activity is not enough to amount to significantly more than the recited judicial exception. See MPEP 2106.05(a, g).
Regarding additional element (ii), the element recited amounts to mere data gathering steps which is found to be insignificant extra-solution as it is merely gathering data prior to and for use by the judicial exception, which is not indicative or integration into a practical application. Further, the additional element (ii) is retrieving information over a network which is well-understood, routine, and conventional activity. See MPEP 2106.05(d). The courts have found adding extra-solution activity and well-understood, routine, and conventional activity is not enough to amount to significantly more than the recited judicial exception. See MPEP 2106.05(a, g).
Therefore, the additional elements amount to insignificant extra solution activity and a mental process which when considered individually and in combination with claim 1, fail to add an inventive concept to the claim and do not amount to significantly more than the judicial exceptions. Therefore claim 8 is ineligible.
Claim 9 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 9 recites,
wherein a priority identified by the prioritization information corresponds to a category for the computing workload.
Regarding limitation (i), it further limits the receiving data over a network “obtain prioritization information for the plurality of pending computing workloads;”, as recited in claim 1, which is merely insignificant extra solution activity and well understood routine and conventional as stated in arguments made for claim 1. Further additional element (i), the element limits the respective priorities to have the specified information that is a component of judicial exceptions from claim 8 and can therefore be performed in the human mind through observation, evaluation, judgement, and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
Therefore, the additional elements amount to insignificant extra solution activity and a mental process which when considered individually and in combination with claim 8 and therefore claim 1, fail to add an inventive concept to the claim and do not amount to significantly more than the judicial exceptions. Therefore claim 9 is ineligible.
Claim 10 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 10 recites,
deallocating the accelerator resource from the first computing workload;
transition, in response to reallocating the accelerator resource to a second computing workload, the first computing workload to a pending state both of which can be performed in the human mind through observation, evaluation, judgement and opinion, with the aid of pen and paper, and are therefore reciting mental processes.
No other additional elements are recited in claim 10.
Accordingly, for the same reasons presented in claim 1, the additional elements are not indicative of integration into a practical application, nor do they amount to significantly more than the recited judicial elements. Thus, claim 10 is ineligible.
Claim 11 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 11 recites,
wherein the first accelerator resource is a graphics processing unit (GPU) or a portion of a GPU.
Regarding limitation (i), the limitation recites generic computer components such that the mental process, i.e. judicial exception, is performed on a generic computer which is not indicative of integration into a practical application. See MPEP 2106.04(a). The courts have found simply requiring the generic computer components to perform generic computer function is well understood routine and conventional. See MPEP 2106.05(d) and 2106.05(f)
Therefore, the additional elements, when considered individually and in combination with claim 1, fail to add an inventive concept to the claim and do not amount to significantly more than the judicial exception. Therefore claim 11 is ineligible
Claim 12 is dependent on claim 1, and therefore inherits the same judicial exceptions recited in claim 1.
Further claim 12 recites,
the second computing workload comprises one or more containers;
and the accelerator resource operates in a containerization environment.
Per Step 2A and 2B
Regarding limitation (i), it states merely indicating a field of use or technological environment in which to apply a judicial exception. Further, the courts have found merely employing generic computer functions to execute an abstract idea, even when limiting the use of the idea to one particular environment, does not add significantly more. See MPEP 2106.05(h).
Regarding limitation (i), it states merely indicating a field of use or technological environment in which to apply a judicial exception. Further, the courts have found merely employing generic computer functions to execute an abstract idea, even when limiting the use of the idea to one particular environment, does not add significantly more. See MPEP 2106.05(h).
Therefore, the additional elements, when considered individually and in combination with claim 1, fail to add an inventive concept to the claim and do not amount to significantly more than the judicial exception. Therefore claim 12 is ineligible
Claim 13 recited a computer-implemented method, comprising steps of the apparatus as claimed in claim 1. Claim 13 does not recite any additional elements beyond those recited in claim 1. Thus, for the same reasons presented with respect to claim 1, claim 13 is rejected because the claimed invention is directed to an abstract idea without significantly more and is not eligible.
Claim 14 is dependent on claim 13, and therefore inherits the same judicial exceptions recited in claim 13.
Further claim 14 recites,
monitoring use of a plurality of accelerator resources allocated to respective computing workloads of a plurality of running computing workloads, the first computing workload being one of the plurality of running computing workloads, the respective accelerator resource for the first computing workload comprising the first accelerator resource;
determining, prior to determining that the use of the first accelerator resource allocated to the first computing workload satisfies the idleness condition, that the use of a second accelerator resource of the plurality of accelerator resources by a third workload of the plurality of running workloads does not satisfy the idleness condition both of which can be performed in the human mind through, observation, evaluation, judgement and opinion, with the aid of pen and paper, and are therefore reciting a mental process.
Accordingly, for the same reasons presented in claim 13, the additional elements are not indicative of integration into a practical application, nor do they amount to significantly more than the recited judicial elements. Thus, claim 14 is not eligible.
Claims 15, 16, 17, 18, and 19 recite substantially the same limitations as those recited in claims 3, 4, 6, 8, and 9 respectively, applied to the method of claim 13. Thus, for the same reasons presented with respect to claims 3, 4, 6, 8, and 9, claims 15, 16, 17, 18, and 19 are directed to an abstract idea without significantly more and are not eligible.
Claim 20 recites one or more non-transitory computer-readable storage media storing programming for execution by the one or more processors, the programming comprising instructions to: perform the steps of the apparatus of claim 1. Thus for the same reasons presented with respect to claim 1, claim 20 is rejected because the claimed invention is directed to an abstract idea without significantly more and is not eligible.
For clarity of the record, the additional elements recited above amount to mere instructions to apply the exception which is neither indicative of integration in a practical application nor amounts to significantly more than the recited judicia exceptions.
Claim Rejections - 35 USC § 103
The following is a quotation of 35 U.S.C. 103 which forms the basis for all obviousness rejections set forth in this Office action:
A patent for a claimed invention may not be obtained, notwithstanding that the claimed invention is not identically disclosed as set forth in section 102, if the differences between the claimed invention and the prior art are such that the claimed invention as a whole would have been obvious before the effective filing date of the claimed invention to a person having ordinary skill in the art to which the claimed invention pertains. Patentability shall not be negated by the manner in which the invention was made.
This application currently names joint inventors. In considering patentability of the claims the examiner presumes that the subject matter of the various claims was commonly owned as of the effective filing date of the claimed invention(s) absent any evidence to the contrary. Applicant is advised of the obligation under 37 CFR 1.56 to point out the inventor and effective filing dates of each claim that was not commonly owned as of the effective filing date of the later invention in order for the examiner to consider the applicability of 35 U.S.C. 102(b)(2)(C) for any potential 35 U.S.C. 102(a)(2) prior art against the later invention.
Claim(s) 1, 3, 6, 11, 12, 13, 15, 17, and 20, is/are rejected under 35 U.S.C. 103 as being unpatentable over Balle et al (U.S. Pub. Number US 20180026905 A1), referred herein as Balle, in view of Li et al (U.S. Pub. No. US 20200159587 A1), referred herein as Li .
Regarding Claim 1, Balle teaches A computing device, comprising: one or more processors; ([0048] Referring now to FIG. 13, the orchestrator server 1240 may be embodied as any type of compute device capable of performing the functions described herein… As shown in FIG. 13, the illustrative orchestrator server 1240 includes a central processing unit (CPU) 1302, a main memory 1304, an input/output (I/O) subsystem 1306, communication circuitry 1308, and one or more data storage devices 1312.)
and one or more non-transitory computer-readable storage media storing programming for execution by the one or more processors, the programming comprising instructions to: ([0083] Example 1 includes an orchestrator server to dynamically allocate resources among a set of managed nodes, the orchestrator server comprising… one or more memory devices having stored therein a plurality of instructions that, when executed by the one or more processors)
monitor use of a first accelerator resource allocated to a first computing workload; ([0058] Referring now to FIG. 14, in the illustrative embodiment, the orchestrator server 1240 may establish an environment 1400 during operation. The illustrative environment 1400 includes… a telemetry monitor 1430.... In the illustrative embodiment, the environment 1400 includes telemetry data 1402 which may be embodied as data indicative of the performance and conditions (e.g., resource utilization) of each managed node 1260 as the managed nodes 1260 execute the workloads assigned to them. [0061] The telemetry monitor 1430, is configured to collect (i.e. monitor) the telemetry data 1402 from the managed nodes 1260 as the managed nodes (e.g. plurality of nodes hence there is a first node) 1260 execute the workloads assigned to them (e.g. plurality of workloads assigned to the nodes, hence there is a first workload assigned to a first node). The telemetry monitor 1430 may actively poll each of the managed nodes 1260 for updated telemetry data 1402 on an ongoing basis or may passively receive telemetry data 1402 from the managed nodes 1260, such as by listening on a particular network port for updated telemetry data 1402. [0046] Each managed node 1260 may be embodied as an assembly of resources (e.g., physical resources 206), such as accelerator resources (e.g., physical accelerator resources 205-2) (e.g. the managed nodes contain accelerator resources to execute workloads))
determine, based on monitoring the use of the first accelerator resource allocated to the first computing workload, that the use of the first accelerator resource allocated to the first computing workload satisfies an idleness condition; ([0077] For example, in the illustrative embodiment, the orchestrator server 1240 compares the present… utilization of each type of resource used and predicted to be used by each workload assigned to a particular managed node 1260 to a threshold amount to determine whether the corresponding resource is underutilized (e.g. whether the managed node is idle) or predicted to be underutilized by the managed node 1260. As indicated in block 1558, the orchestrator server 1240 identifies (i.e. determines) any overallocation (i.e., underutilization) of compute and/or accelerator resources by each managed node 1260. (e.g. the managed node is idle when compared to the threshold and therefore satisfies an idleness condition))
Additionally Balle teaches:
Deallocating resources that were determined to be idle [0080]
Balle does not teach and reallocate, based at least on determining that the use of the first accelerator resource allocated to the first computing workload satisfies the idleness condition, the first accelerator resource to a second computing workload, the second computing workload being a pending computing workload.
However Li teaches and reallocate, based at least on determining that the use of the first accelerator resource allocated to the first computing workload satisfies the idleness condition, the first accelerator resource to a second computing workload, the second computing workload being a pending computing workload. ([0068] In response to determining, according to step 510, that one or more currently running workloads are appropriate to be preempted by a pending workload, the scheduler may signal the corresponding host or hosts on which the currently running workloads are running to stop processes of the currently running workloads. In such a way, resources previously reserved on the host or hosts for the currently running workloads are released (e.g. first accelerator resource is deallocated). Next, at step 620, the pending workload (i.e. second workload being a pending workload) is started on the host or hosts using at least part of the released resources (e.g. the released resources are reallocated to the second pending). As such, the pending workload can operate normally without influencing other workloads that will still be running on the host or hosts.)
Balle and Li are analogous art to the claimed invention because they are reasonable pertinent to the inventive concept of dynamically optimizing processor resources for tasks. It would have been obvious before the effective filing date of the claimed invention to combine determining that a workload should release its resources such that the resources should be reallocated to a pending workload as in Li, with a reasonable expectation of success, wherein a system that monitors idleness of accelerator resources determines a threshold is met while executing the workload and further deallocates the resources the accelerator resources as taught in Balle, could further redistribute the resources to a preferred second pending workload as taught in Li. A person having ordinary skill in the art would have been motivated to make this combination to improve resource utilization and run pending workloads efficiently without influencing other running workloads (Li [0054]-[0055])
Regarding Claim 3, Balle and Li teach The computing device of Claim 1. Balle further teaches wherein the instructions to determine that the use of the first accelerator resource allocated to the first computing workload satisfies an idleness condition comprise instructions to determine that the use of the first accelerator resource does not satisfy an idleness threshold. ([0077] For example, in the illustrative embodiment, the orchestrator server 1240 compares the present and predicted utilization of each type of resource used and predicted to be used by each workload assigned to a particular managed node 1260 to a threshold amount (e.g., 80% of available capacity) to determine whether the corresponding resource is underutilized (i.e. idleness condition) or predicted to be underutilized by the managed node 1260. As indicated in block 1558, the orchestrator server 1240 identifies any over allocation (i.e., underutilization) of compute and/or accelerator resources by each managed node 1260. (e.g. the resource utilization is below the threshold and further satisfies the idleness condition))
Regarding Claim 6, Balle and Li teach The computing device of Claim 1. Balle further teaches wherein the instructions to monitor use of the first accelerator resource allocated to the first running computing workload comprise instructions to receive accelerator usage information from the first accelerator resource. ([0061] The telemetry monitor 1430, which may be embodied as hardware, firmware, software, virtualized hardware, emulated architecture, and/or a combination thereof as discussed above, is configured to collect (e.g. receive) the telemetry data 1402 from the managed nodes 1260 as the managed nodes 1260 execute the workloads assigned to them.)
Regarding Claim 11, Balle and Li teach The computing device of Claim 1. Balle further teaches wherein the first accelerator resource is a graphics processing unit (GPU) or a portion of a GPU. ([0046] Each managed node 1260 may be embodied as an assembly of resources such as accelerator resources (e.g., physical accelerator resources 205-2); [0059]… data indicative of the allocations of resources among the managed nodes 1260 at any given time during the execution of the workloads, including the… accelerator (e.g., field programmable gate array (FPGA), application specific integrated circuit (ASIC), graphics processing unit (GPU), or other specialized hardware for accelerating a type of computation) resources (accelerating a type of computation or workload would encompass using a GPU (i.e. first accelerator resource)))
Regarding Claim 12, Balle and Li teach The computing device of Claim 1. Balle further teaches wherein: the second computing workload comprises one or more containers; and the accelerator resource operates in a containerization environment. ([0046] Each managed node 1260 may be embodied as an assembly of resources (e.g., physical resources 206), such as accelerator resources (e.g., physical accelerator resources 205-2); The orchestrator server 1240 may support a cloud operating environment, such as OpenStack, and the managed nodes 1250 may execute one or more applications or processes (i.e., workloads), such as in virtual machines or containers, on behalf of a user of the client device 1220. (Managed nodes host accelerator resources to process the container workloads as such the nodes execute the workloads inside containers and the underlying accelerator resource is provisioned and utilized within that containerized environment))
Claims 13 and 20 recite substantially the same limitations as claim 1, applied to the method and product claim. As such, Claim 13 and 20 are rejected as being unpatentable over Balle in view of Li for the same reasons presented with respect to claim 1.
Claims 15 and 17 recite substantially the same limitations as claims 3 and 6 respectively, applied to the method claim of 13. As such, claim 15 and 17 are rejected as being unpatentable over Balle in view of Li for the same reasons presented with respect to claims 3 and 6.
Claim 2 is rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of Ionescu et al (U.S. Pub. No. US 20250245071 A1), referred herein as Ionescu.
Balle and Li teach The computing device of Claim 1. Li further teaches the first workload comprises first workload information that comprises: a priority associated with the first workload; ([0065] Priorities of the currently running workloads (e.g. first workload) and the pending workload may be predetermined or may be calculated and adjusted at runtime.) and the second workload comprises second workload information that comprises: and a priority associated with the second workload. ([0065] Priorities of the currently running workloads and the pending workload (e.g. second workload) may be predetermined or may be calculated and adjusted at runtime.)
Li does not teach a category associated with the first workload; and a start time associated with the first workload; a category associated with the second workload;
However Ionescu (US 20250245071) teaches a category associated with the first workload; and a start time associated with the first workload; a category associated with the second workload; ([0134] Referring now to FIG. 10, an example of data components in a task queue 220 is provided. The task queue includes a list of tasks 1002 (i.e. first workload), 1004(i.e. second workload), 1006. Each task includes data components (e.g. workload information). In some cases, the data components for each task includes: a task type (i.e. category), a task priority, a start time, and a process status.)
Ionescu is analogous to the claimed invention as it is reasonably pertinent to the inventive concept of optimizing allocating resources to a plurality of tasks based on their priority. It would have been obvious before the effective filing date of the claimed invention to combine scheduling tasks by their priority such that each task contains information corresponding to their priority, category, and start time, as in Ionescu, with a reasonable expectation of success, where a system that would schedule a second computing workload with a specified priority to preempt the resources of first computing workload based on the idleness of a compute resource, as in Balle and Li, could further include the workloads to have information pertaining to their category and start time as taught in Ionescu. A person having ordinary skill in the art would have been motivated to make this combination to improve resource utilization and further strategize preemption decisions (Li [0054], [0055], [0058]) and ensure resources allocated to a task are capable of performing the task(Ionescu [0050]).
Claims 4 and 16 are rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of MacNamara et al (US 20250013507 A1), referred herein as MacNamara.
Regarding Claim 4, Balle and Li teach The computing device of Claim 3. Balle further teaches wherein the instructions to determine that the use of the first accelerator resource does not satisfy the idleness threshold comprise instructions to: access accelerator usage information for the first accelerator resource; ([0058]The illustrative environment 1400 includes… a telemetry monitor 1430.... In the illustrative embodiment, the environment 1400 includes telemetry data 1402 which may be embodied as data indicative of the performance and conditions (e.g., resource utilization) of each managed node 1260 as the managed nodes 1260 execute the workloads assigned to them (e.g. accelerator resource usage by the workload). [0061] The telemetry monitor 1430, is configured to collect (i.e. capable of accessing) the telemetry data 1402 from the managed nodes 1260 as the managed nodes execute the workloads assigned to them. The telemetry monitor 1430 may actively poll each of the managed nodes 1260 for updated telemetry data 1402 on an ongoing basis or may passively receive telemetry data 1402 from the managed nodes 1260, such as by listening on a particular network port for updated telemetry data 1402.)
Neither Balle nor Li teaches determine, according to the accelerator usage information, whether average accelerator usage over a time period satisfies an idleness threshold; and determine, based at least on determining that the average accelerator usage over a time period does not satisfy the idleness threshold, that the use of the first accelerator resource allocated to the first computing workload satisfies an idleness condition.
However, MacNamara teaches determine, according to the accelerator usage information, whether average accelerator usage over a time period satisfies an idleness threshold; and determine, based at least on determining that the average accelerator usage over a time period does not satisfy the idleness threshold, that the use of the first accelerator resource allocated to the first computing workload satisfies an idleness condition. ([0050] The power recommender 404 may use recommendation system rules to identify the idle status of the core (e.g. if the resource satisfies an idleness condition)… a core/CPU (e.g. accelerator resource) is considered idle (e.g. satisfies an idleness condition) if, during a 24-hour time window, the CPU/core average utilization over time is less than (e.g. does not satisfy) a threshold amount, such as 1%-10%).
MacNamara is analogous to the claimed invention as it is reasonably pertinent to dynamically optimizing compute resources. It would’ve been obvious before the effective filing date of the claimed invention to combine monitoring telemetry data such as average processor usage during a time period to determine if a processor is idle such that usage is less than (does not satisfy) a given threshold as in MacNamara, with a reasonable expectation of success, where a system monitors resource telemetry data to determine if a processor is idle based on not satisfying a threshold and therefore reallocates the resources to a second workload as in Balle and Li could determine if the threshold is satisfied by considering the average processor utilization over a time period as in MacNamara. A person having ordinary skill in the art would be motivated to make this combination to implement automatic identification and power optimization of idle resources (MacNamara [0025]).
Claim 16 recites substantially the same limitations as claims 4, applied to the method claim of 13. As such, claim 16 is rejected as being unpatentable over Balle in view of Li in view of MacNamara for the same reasons presented with respect to claim 4.
Claim 5 is rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of Ionescu in view of Park et al (US 20260120697 A1), referred herein as Park.
Regarding Claim 5, Balle, Li, and Ionescu teach The computing device of Claim 4.
However Balle and Li do not teach wherein the idleness threshold is zero.
However Park (US 20260120697 A1) teaches wherein the idleness threshold is zero([0123] For example, as the network performance and/or hardware performance increases, the priority of the external electronic devices 102-1, 102-2, and 102-3 may increase. Whether an operation state is a sleep state/idle state or a busy state may be determined based on a processor usage rate and a memory usage rate… and when the processor usage rate (e.g. idleness threshold) is about 0%, it may indicate an idle state.)
Park is analogous art as it is reasonable pertinent to the inventive concept of dynamically allocating resources based on their idleness. It would have been obvious before the effective filing date of the claimed invention to combine determining that a device is idle if its usage is 0% as in Park, with a reasonable expectation of success, where a system determining that an accelerator is idle to further deallocate its resources, is based on the average accelerator use not satisfying an idleness threshold as in Balle, Li, and MacNamara, would consider an accelerator to not satisfy an idleness threshold, and therefore be idle, if the accelerator’s usage was 0% as in park. A person having ordinary skill in the art would have been motivated to make this combination to determine an optimal device to process a task (Park [0008]).
Claim 7 is rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of Dawson et al (U.S. Pub. No. US 20180011788), referred herein as Dawson.
Regarding Claim 7, Balle and Li teach The computing device of Claim 1.
Balle and Li do not teach wherein the programming further comprises instructions to determine, prior to reallocating the accelerator resource to the second computing workload, that the first workload has been running for a toleration time period.
However Dawson teaches wherein the programming further comprises instructions to determine, prior to reallocating the accelerator resource to the second computing workload, that the first workload has been running for a toleration time period. ([0027] An application 132 (i.e. workload) is running on server 130 that requires resources which have been allocated to a heap 142 in the memory 140. The run time module 150 starts an interval, which is a predetermined time period or time interval, in which the counter 152 counts the number of events or triggered events that occurs during the interval (S200). The counter 152 determines if the interval has finished (S205) and calculated the total number of events that occurred during the interval (S210). (e.g. The counter determines if the application has been at least running for the interval time window) …the idle module 154 determines if the number of events is below a threshold value (S220). When the idle module 154 determines that the number of events is above the threshold value then the idle module 154 set the status of application 132 as active and starts the interval period over again (S225). [0028] When the idle module 154 determines that the number of events is below the threshold value (e.g. after the interval has completed), the idle module 154 determines what the current status of the application 132 is (S230). [0048] Cloud computing is a model of service delivery for enabling convenient, on-demand network access to a shared pool of configurable computing resources (e.g., networks, network bandwidth, servers, processing, memory, storage, applications, virtual machines, and services) that can be rapidly provisioned and released with minimal management effort or interaction with a provider of the service.)
Dawson is analogous art to the claimed invention as it is reasonably pertinent to the inventive concept of determining idle status of workloads to optimize resources. It would have been obvious before the effective filing date of the claimed invention to combine monitoring a workload for a given time interval such that when the interval completes it will be determined the idleness of a workload, with a reasonable expectation to success, where a system that monitors a resource allocated to a workload would determine if it is idle and therefore would deallocate the resources and reallocate them to a pending workload as in Balle and Li, could allow the workload to run for a time interval before making the determination of idleness, as in Dawson. A person of ordinary skill in the art would have been motivated to make this combination to ensure that the detection of idleness is safeguarded by a time window that can be set across all workloads for fair management.
Claims 8, 9, 18, and 19 are rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of Wong (WIPO Pub. No. WO2023048987A1), referred herein as Wong.
Regarding Claim 8, Balle and Li teach The computing device of Claim 1, Li further teaches wherein: the second computing workload is one of a plurality of pending computing workloads; ([0058] The scheduler 410 may maintain a scheduling queue to receive batch jobs. Batch jobs get scheduled to run in an order according to various known principles such as first-in-first-out (FIFO), highest priority first or shortest execution time first. Each pending job 430 (see in figure 4 there are multiple pending jobs in the queue hence a plurality of pending computing workloads) in the scheduling queue has a resource requirement indicating how many resources it will need.)
Li further teaches:
[0064] In some embodiments, the preemptive scheduling method based on releasable resources of currently running workloads to be preempted may be implemented in further consideration of priorities of the currently running workloads and the pending workload. Specifically, the one or more currently running workloads to be preempted may have lower priorities than that of the preemptive pending workload.
Balle and Li do not teach, and the programming further comprises instructions to: access a pending workload queue that comprises the plurality of pending computing workloads; obtain prioritization information for the plurality of pending computing workloads; and determine a selected pending workload to be the second computing workload according to respective priorities of the plurality of pending computing workloads.
However Wong teaches and the programming further comprises instructions to: access a pending workload queue that comprises the plurality of pending computing workloads; ([0070] In the example method of FIG. 7, scheduling 620 execution of the workload based on the priority level includes assigning 710 the workload to a job scheduling queue among a plurality of job scheduling queues each corresponding to a priority level. (e.g. capable of accessing a queue) For example, the job scheduler can select work items for execution from the job queue defined for priority level ‘ 1’ workloads (e.g. queue contains a plurality of pending workloads) before selecting work items from the priority level ‘2’ job queue, and then select work items for execution from the priority level ‘2’ job queue before selecting work items from the priority level ‘3’ job queue, and so on. )
obtain prioritization information for the plurality of pending computing workloads; ([0037] For each processing resource there is a job scheduler 194 that dispatches workloads (i.e. plurality of pending workloads) for execution on the processing resource. The job schedulers 194 receive (i.e. obtain) information from the resource manager 170 about incoming workloads from workload initiators. [0067] The example method of FIG. 6 also includes receiving 610, by a job scheduler, the priority level associated with the workload.)
and determine a selected pending workload to be the second computing workload according to respective priorities of the plurality of pending computing workloads. ([0013] To address these limitations, the present disclosure provides a mechanism for a priority-based resource scheduling in which a workload is associated with a priority assignment based on workload characteristics. For example, real-time workloads and non- real-time workloads can be assigned distinct priority levels, which can be used by a job scheduler to provide hardware access for the workload based on the assigned priority. [0070] For example, the job scheduler can select work items for execution from the job queue defined for priority level ‘ 1’ workloads before selecting work items from the priority level ‘2’ job queue, and then select work items for execution from the priority level ‘2’ job queue before selecting work items from the priority level ‘3’ job queue, and so on. (i.e. a higher priority workload is selected to be a second computing workload before the execution of a lower priority workload))
Wong is analogous art to the claimed invention as it is reasonably pertinent to the inventive concept of scheduling tasks amongst resources based on their priority. It would have been obvious before the effective filing date of the claimed invention to combine accessing a queue of workloads to schedule higher priority tasks before lower priority tasks, with a reasonable expectation of success, where a system that determines a resource allocated to a task is idle and therefore will reallocate it’s resources to a pending task in a queue with each task having a respective priority as in Balle and Li, could choose the pending task based on its priority according to the priorities of the pending workloads, as in Wong. A person having ordinary skill in the art would have been motivated to make this combination to improve resource utilization and further strategize preemption decisions (Li [0054], [0055], [0058]) and allocate capable resources to the workloads and has full context when scheduling a workload (Wong [0010]-[0011]).
Regarding Claim 9, Balle and Li teach The computing device of Claim 8.
Balle and Li do not teach wherein a priority identified by the prioritization information corresponds to a category for the computing workload.
However Wong teaches wherein a priority identified by the prioritization information corresponds to a category for the computing workload. ([0020] In some implementations, determining, based on the characteristics of the workload and one or more policies, a priority level for the workload includes identifying, based on the characteristics of the workload, a job classification (i.e. category) for the workload. In these implementations, determining the priority level also includes identifying, from the one or more policies, a priority definition corresponding to the job classification (i.e. category))
Wong is analogous art to the claimed invention as it is reasonably pertinent to the inventive concept of scheduling tasks amongst resources based on their priority. It would have been obvious before the effective filing date of the claimed invention to combine accessing a queue of workloads to schedule tasks based on their priority level which corresponds to a certain category, with a reasonable expectation of success, where a system that determines a resource allocated to a task is idle and therefore will reallocate it’s resources to a pending task in a queue as in Balle and Li, could choose the pending task based on its priority according to the priorities, corresponding to a category, of the pending workloads, as in Wong. A person having ordinary skill in the art would have been motivated to make this combination to allocate capable resources to the workloads and has full context when scheduling a workload (Wong [0010]-[0011])
Claims 18 and 19 recite substantially the same limitations as claims 8 and 9 respectively, applied to the method claim of 13. As such, claims 18 and 19 are rejected as being unpatentable over Balle in view of Li in view of Wong for the same reasons presented with respect to claims 8 and 9.
Claim 10 is rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of Chatterjee et al (U.S. Pub. No. 20240070047).
Balle and Li teach The computing device of Claim 1. Balle further teaches wherein: reallocating the accelerator resource to a second computing workload comprises deallocating the accelerator resource from the first computing workload; ([0080] As indicated in block 1580, in applying the determined adjustments, the orchestrator server 1240, in the illustrative embodiment, may issue one or more requests to deallocate underutilized resources identified in block 1556 of FIG. 16.)
Balle and Li do not teach, and the programming further comprises instructions to transition, in response to reallocating the accelerator resource to a second computing workload, the first computing workload to a pending state.
However Chatterjee teaches and the programming further comprises instructions to transition, in response to reallocating the accelerator resource to a second computing workload, the first computing workload to a pending state. ([0059] In at least one embodiment, scheduler 102 schedules a queued task to compute node(s) 104 by preempting one or more running tasks being executed on compute node(s) 104. In at least one embodiment, scheduler 102 preempts one or more tasks running (i.e. first computing workload) on compute node(s) 104 by halting, and/or pausing tasks such that they are transitioned back to a queued state (e.g. the first running workload is now pending as it is queued for execution). In one or more embodiments, once a previously running task has been transitioned… 102, it is scheduled and/or executed in association to compute node(s) 104 at a later instance of time.)
Chatterjee is analogous art to the claimed invention as it is reasonably pertinent to dynamically optimizing processor resources. It would have been obvious to combine transitioning a first task to a queued state once it’s processes have been halted because it has been preempted by a second task as in Chatterjee, with a reasonable expectation of success, where a system that determines idleness of a first workload, further halts the workloads execution, and allocates it’s resources to a second computing workload, as in Balle and Li, could further transition the first workload back to a pending state to be executed at a later time, as in Chatterjee. A person having ordinary skill in the art would have been motivated to make this combination to optimize scheduling and eviction of tasks in a computer cluster (Chatterjee [0002])
Claim 14 is rejected under 35 U.S.C. 103 as being unpatentable over Balle in view of Li in view of Subramaniam et al (U.S. Patent No. 10795736), referred herein as Subramaniam.
Balle and Li teach The computer-implemented method of Claim 13. Balle further teaches comprising: monitoring use of a plurality of accelerator resources allocated to respective computing workloads of a plurality of running computing workloads, the first computing workload being one of the plurality of running computing workloads, the respective accelerator resource for the first computing workload comprising the first accelerator resource;
Balle and Li do not teach determining, prior to determining that the use of the first accelerator resource allocated to the first computing workload satisfies the idleness condition, that the use of a second accelerator resource of the plurality of accelerator resources by a third workload of the plurality of running workloads does not satisfy the idleness condition.
However Subramaniam teaches determining, prior to determining that the use of the first accelerator resource allocated to the first computing workload satisfies the idleness condition, that the use of a second accelerator resource of the plurality of accelerator resources by a third workload of the plurality of running workloads does not satisfy the idleness condition. ( (Page 10 Col 10 lines 32-39) The resource usage data from each computing resource or host machine (e.g., server 115) can include information such as the current processor utilization, the current memory utilization, the current network bandwidth utilization, or other utilization metrics for the device. In some instances, the resource usage data can be provided by the individual devices in the computing cluster 106 on a periodic basis. (e.g. overtime servers are reporting their resource usage corresponding to respective workloads); (Page 11 Col 11 lines 15-20) However, if the resource management service 142 proceeds to step 413, the resource management service 142 can then determine whether the computing cluster 106 has excess capacity. For instance, the computing cluster 106 can have computing resources or host machines (e.g., servers 115) which are unutilized or underutilized. Removing such unutilized or underutilized servers 115 from the computing cluster 106 cannot noticeably impact the performance of the workloads 145 assigned to the computing cluster 106. (e.g. idle resources allocated to the computing workload). (Page 11 col 11 lines 36-45) If one of the resource usage rules 131 were predicted to be violated upon removal of a server 115, then the resource management service 142 could conclude that the computing cluster 106 did not have any excess computing capacity (e.g. the resources were found to be utilized and therefore will not be deallocated from the workload). (Page 11 Col 11 lines 58-65) If the resource management service 142 proceeds to step 416, the resource management service 142 first sends a command to the computing cluster 106 to redistribute one or more workloads 145 within the computing cluster 106. The redistribution of the workloads 145 to other servers 115 within the computing cluster 106 allows for a server 115 to be removed from the computing cluster 106 without impacting the workloads 145. (Page 11 Col 11-12, lines 66-67 and Lines 0-19) Then at step 419, the resource management service 142 can send a command to the computing cluster 106 to power-off a server 115 or otherwise cause the server 115 to enter a low-power or idle state, such as a maintenance mode. When the server 115 powers-off or enters the low-power or idle state, the server 115 can no longer be available to the computing cluster 106 for use by one or more of the workloads 145. In some instances, the resource management service 142 can receive multiple host identifiers 138. Proceeding to step 423, the resource management service 142 adds the received host identifier 138 to the free host queue 133. The process then ends. (e.g. resources are deallocated if they are determined to be idle and as such can be reallocated to alternate computing clusters and workloads) )
Subramaniam is analogous to the claimed invention as it is reasonably pertinent to the inventive concept of efficient resource utilization according to idleness. It would have been obvious before the effective filing date of the claimed invention to combine monitoring resource usage across different resources to identify them as idle or not, as in Subramaniam, with a reasonable expectation of success, where a system that identifies resource usage across workloads such that when a resource is determined to be idle it is reallocated to a pending workload as in Balle and Li, could, while obtaining resource usage for the given resources allocated to workloads across computing clusters (i.e. managed nodes), determine that the resources for a given workload are utilized and do not satisfy the rules to be idle nor should be added to the free host queue before determining that another computing cluster has an underutilization of the resources allocated to another workload and as such are idle, as in Subramaniam. A person having ordinary skill in the art would have been motivated to make this combination to automate the dynamic redistribution of resources across workloads (Subramaniam Page 6, Col 1, lines 16-26).
Conclusion
The prior art made or record and not relied upon is considered pertinent to applicant’s disclosure.
Farrel et al (U.S. Pub. No. 20130185739) teaches the use of a grace period before a context switch. See [110]
Kuperman (U.S. Pub. No. 20260044390) teaches the use of a Graphical User Interface to see metrics of pod and cluster utilization in a containerized environment. See Figures 4-8.
Sajeepa (U.S. Pub. No. 20240370190) teaches the use of a plurality of management systems for containerized environments like Docker Swarm, and Kubernetes. See [191] and [227].
Mathur (U.S. Pub. No. 20190102216) teaches the use of an initialization period to warm up a process prior to polling the state of a workload. See Figure 3B times T1-T2.
Any inquiry concerning this communication or earlier communications from the examiner should be directed to Kayla E Conrad whose telephone number is (571)272-0684. The examiner can normally be reached Monday Through Friday 8 a.m. - 4p.m..
Examiner interviews are available via telephone, in-person, and video conferencing using a USPTO supplied web-based collaboration tool. To schedule an interview, applicant is encouraged to use the USPTO Automated Interview Request (AIR) at http://www.uspto.gov/interviewpractice.
If attempts to reach the examiner by telephone are unsuccessful, the examiner’s supervisor, Kevin Young can be reached at (571)270-3180. The fax phone number for the organization where this application or proceeding is assigned is 571-273-8300.
Information regarding the status of published or unpublished applications may be obtained from Patent Center. Unpublished application information in Patent Center is available to registered users. To file and manage patent submissions in Patent Center, visit: https://patentcenter.uspto.gov. Visit https://www.uspto.gov/patents/apply/patent-center for more information about Patent Center and https://www.uspto.gov/patents/docx for information about filing in DOCX format. For additional questions, contact the Electronic Business Center (EBC) at 866-217-9197 (toll-free). If you would like assistance from a USPTO Customer Service Representative, call 800-786-9199 (IN USA OR CANADA) or 571-272-1000.
/Kayla E Conrad/Examiner, Art Unit 2194 /KEVIN L YOUNG/Supervisory Patent Examiner, Art Unit 2194