Notice of Pre-AIA or AIA Status
The present application, filed on or after March 16, 2013, is being examined under the first inventor to file provisions of the AIA .
Drawings
The drawings filed on 11/22/2024 are accepted by the examiner.
Information Disclosure Statement
The information disclosure statement (IDS) submitted on 11/22/2024 is in compliance with the provisions of 37 CFR 1.97. Accordingly, the information disclosure statement is being considered by the examiner.
Claim Rejections - 35 USC § 103
The following is a quotation of 35 U.S.C. 103 which forms the basis for all obviousness rejections set forth in this Office action:
A patent for a claimed invention may not be obtained, notwithstanding that the claimed invention is not identically disclosed as set forth in section 102, if the differences between the claimed invention and the prior art are such that the claimed invention as a whole would have been obvious before the effective filing date of the claimed invention to a person having ordinary skill in the art to which the claimed invention pertains. Patentability shall not be negated by the manner in which the invention was made.
The factual inquiries for establishing a background for determining obviousness under 35 U.S.C. 103 are summarized as follows:
1. Determining the scope and contents of the prior art.
2. Ascertaining the differences between the prior art and the claims at issue.
3. Resolving the level of ordinary skill in the pertinent art.
4. Considering objective evidence present in the application indicating obviousness or nonobviousness.
Claim(s) 1, 3, 5-6, 8-9, 11, 13-14 and 16-20 is/are rejected under 35 U.S.C. 103 as being unpatentable over US20210132591 to Lu, in view of US20090276061 to Sheth et al. (hereinafter “Sheth”).
As for claim 1, Lu substantially discloses a plant-wide optimization system (Lu, see [0004]), comprising:
a user interface configured to receive values for at least one of a plurality of controlled variables and a plurality of manipulated variables for a plant (Lu, see [0044] for operator stations allow the user to adjust the operation of the sensors 102a, actuators 102b, controllers 106, or machine-level controllers 114);
at least one processor (Lu, see [0006]); a non-transitory storage medium that stores an optimization program (Lu, see [0006]), and a flowsheet model (Lu, see Fig. 2A, Fig. 2B and [0065]-[0072]), the flowsheet model having a gain matrix (Lu, see [0074]);
wherein the flowsheet model includes a plurality of models that represent a plurality of process units or routing elements in the plant, the plant comprising at least one process controller coupled to field devices of the plurality of process units (Lu, see Fig. 2A, Fig. 2B and [0065]-[0072]),
wherein each of the plurality of process units comprise equipment for converting a raw material or an intermediate material into another material (Lu, see Fig. 2A, Fig. 20 and [0141]);
wherein the plurality of models are interconnected in the planning model to create a plant-wide model with a plurality of paths between a plurality of inlets of the plant and a plurality of outlets (Lu, see Fig. 2A, Fig. 2B and [0065]-[0072]);
wherein the flowsheet model includes the plurality of manipulated variables and the plurality of controlled variables, each associated with one or more of the plurality of process units or routing elements (Lu, see Fig. 2A, Fig. 2B and [0065]-[0072]);
wherein each gain in the gain matrix relates a change in one of the plurality of manipulated variables to a corresponding change in one of the plurality of controlled variables (Lu, see [0104]-[0107]); and
wherein the optimization program, when executed by the at least one processor, causes the at least one processor to perform a method (Lu, see [0006]) including:
receiving the values for the at least one of the plurality of controlled variables and the plurality of manipulated variables from the user interface (Lu, see [0044] for operator stations allow the user to adjust the operation of the sensors 102a, actuators 102b, controllers 106, or machine-level controllers 114);
determining an optimal operating point using the gain matrix of the flowsheet model for one or more of the plurality of manipulated variables using the received values (Lu, see [0160]-[0162]); and
causing the at least one process controller to control the plurality of process units in accordance with the optimal operating point for the one or more of the plurality of manipulated variables (Lu, see [0160]-[0162]).
Lu does not explicitly disclose receive values being limits for controlled/manipulated variables, wherein each gain is generated as a product of individual, analytical gains for each process unit and routing element between the one of the plurality of manipulated variables and the one of the plurality of controlled variables in the model.
However, Sheth in an analogous art discloses wherein each gain is generated as a product of individual, analytical gains for each process unit and routing element between the one of the plurality of manipulated variables and the one of the plurality of controlled variables in the model (Sheth, see [0031]-[0036]).
Therefore, it would have been obvious to a person of ordinary skill in the art before the effective filing date of the claimed invention to incorporate teaching of Sheth into the system of Lu. The modification would be obvious because one of the ordinary skill in the art would want to provide improved or new operating conditions or operating condition targets (Sheth, see [0007]).
The combination of Lu and Sheth does not explicitly disclose receive values being limits for controlled/manipulated variables. However, Wojsznis in an analogous art discloses receive values being limits for controlled/manipulated variables (Wojsznis, see [0038]-[0040]).
Therefore, it would have been obvious to a person of ordinary skill in the art before the effective filing date of the claimed invention to incorporate teaching of Wojsznis into the combination of Lu and Sheth. The modification would be obvious because one of the ordinary skill in the art would want to quickly control to a desired operational point in response to disturbances and noise within the process (Wojsznis, see [0011]).
Claim 9 is a method claim corresponds to the system claim 1, it is therefore rejected under similar reasons set forth in the rejection of claim 1.
Claim 17 is a CRM claim corresponds to the system claim 1, it is therefore rejected under similar reasons set forth in the rejection of claim 1.
As per claim 3, the rejection of claim 1 is incorporated, Lu further discloses the plurality of models includes a model of a junction configured to receive at least two inlet streams, combine the at least two inlet streams, and output one outlet stream (Lu, see Fig. 2B, [0065]-[0071] and [0102]); wherein each inlet stream receives a unique inlet flow and has at least one property; wherein the one outlet stream provides a variable outlet flow which is equal to a sum of each unique inlet flow (Lu, see [0167]-[0168]; wherein the one outlet stream has the at least one property; wherein each of the at least one property of the one outlet stream, equals a flow weighted average of a property of each of the at least two inlet streams (Lu, see [0107]-[0109]); wherein a first gain of each outlet stream equals one and is a change in the variable outlet flow divided by a change in one unique inlet flow (Lu, see [0104]-[0107]); wherein a second gain equals a difference between a unique property of a unique inlet flow and the unique property of an outlet stream flow, divided by the variable outlet flow (Lu, see [0104]-[0107]); and wherein a third gain, between an outlet property and an inlet property, equals a ratio of the inlet flow to the outlet flow (Lu, see [0104]-[0107]).
Claim 11 is a method claim corresponds to the system claim 3, it is therefore rejected under similar reasons set forth in the rejection of claim 3.
As per claim 5, the rejection of claim 1 is incorporated, Lu further discloses wherein the plurality of models includes a user-supplied model for a blender that employs a nonlinear mixing rule, wherein the user-supplied model includes property gains, wherein a first property gain relates an outlet property to an inlet property and a second property gain relates an output property to an inlet flow (Lu, see Fig. 8 and [0104]-[0107]).
Claim 13 is a method claim corresponds to the system claim 5, it is therefore rejected under similar reasons set forth in the rejection of claim 5.
As per claim 6, the rejection of claim 1 is incorporated, Lu further discloses the plurality of models includes a model of a tank configured to receive one or more inlet streams, each inlet stream having a flow with one or more properties, a volume of material in the tank with one or more properties, and an outlet flow with the same properties as the volume of material in the tank (Lu, see Fig. 9 and [0108]-[0111]); the model further including a plurality of gains, wherein the plurality of gains include one or more of: a first gain that represents a change in the volume of material in the tank to the inlet flow; a second gain that represents a change in the volume of the material in the tank to the outlet flow; a third gain that represents a change in one of the one or properties of the material in the tank to the inlet flow; a fourth gain that represents a change in one of the one or more properties of the material in the tank to a property of the inlet flow; and a fifth gain represents a change in one of the one or more properties of the outlet flow to one of the one or more properties of the material in the tank (Lu, see Fig. 9 and [0104]-[0111], it is noted that “wherein the plurality of gains include one or more of: a first gain that represents a change in the volume of material in the tank to the inlet flow; a second gain that represents a change in the volume of the material in the tank to the outlet flow; a third gain that represents a change in one of the one or properties of the material in the tank to the inlet flow; a fourth gain that represents a change in one of the one or more properties of the material in the tank to a property of the inlet flow; and a fifth gain represents a change in one of the one or more properties of the outlet flow to one of the one or more properties of the material in the tank” can be interpreted as “wherein the plurality of gains include gain that represents a change in the volume of material in the tank to the inlet flow because the usage of “one or more of”).
Claim 14 is a method claim corresponds to the system claim 6, it is therefore rejected under similar reasons set forth in the rejection of claim 6.
As per claim 8, the rejection of claim 1 is incorporated, Lu further discloses wherein each model of the plurality of models includes one or more of a first gain, a second gain and a third gain; wherein: the first gain equals a ratio of an outlet flow to an inlet flow; the second gain equals a ratio of a property of an outlet flow divided by a property of an inlet flow; and the third gain equals a ratio of a property of an outlet flow and an inlet flow (Lu, see Fig. 9 and [0104]-[0111]).
Claim 16 is a method claim corresponds to the system claim 8, it is therefore rejected under similar reasons set forth in the rejection of claim 8.
Claim 18 is a CRM claim corresponds to the system claim 8, it is therefore rejected under similar reasons set forth in the rejection of claim 8.
As per claim 19, the rejection of claim 17 is incorporated, Lu further discloses the flowsheet model includes model for a blender (Lu, see [0102]).
As per claim 20, the rejection of claim 19 is incorporated, Lu further discloses wherein the plurality of models includes a user-supplied model for a blender that employs a nonlinear mixing rule, wherein the user-supplied model includes property gains, wherein a first property gain relates an outlet property to an inlet property and a second property gain relates an output property to an inlet flow (Lu, see Fig. 8 and [0104]-[0107]).
Claim(s) 7 and 15 is/are rejected under 35 U.S.C. 103 as being unpatentable over Lu, in view of Sheth, in view of Wojsznis, further in view of US20180365353 to Devereux et al. (hereinafter “Devereux”).
As per claim 7, the rejection of claim 1 is incorporated, the combination of Lu, Sheth and Wojsznis does not explicitly disclose the plurality of models includes a model of a Tear that represents a recycle stream in a plant, wherein an outlet stream of a downstream model is returned to an inlet stream of an upstream model to recycle the outlet stream of the downstream model. However, Devereux in an analogous art discloses the plurality of models includes a model of a Tear that represents a recycle stream in a plant, wherein an outlet stream of a downstream model is returned to an inlet stream of an upstream model to recycle the outlet stream of the downstream model (Devereux, see Fig. 1, Fig. 3 and [0021]-[0030]).
Therefore, it would have been obvious to a person of ordinary skill in the art before the effective filing date of the claimed invention to incorporate teaching of Devereux into the combination of Lu, Sheth and Wojsznis. The modification would be obvious because one of the ordinary skill in the art would want to change process parameter setting(s) to modify the operating conditions to achieve a desired performance (Devereux, see [0030]).
Claim 15 is a method claim corresponds to the system claim 7, it is therefore rejected under similar reasons set forth in the rejection of claim 7.
Allowable Subject Matter
Claims 2, 4, 10 and 12 are objected to as being dependent upon a rejected base claim, but would be allowable if rewritten in independent form including all of the limitations of the base claim and any intervening claims.
The following is an examiner’s statement of reasons for allowance:
Claims 2 and 10
Regarding claims 2 and 10, the combination of the cited prior arts does not describe:
wherein the plurality of models includes a model of a splitter configured to receive one inlet stream, and configured to output one outlet swing stream and at least one outlet non-swing stream; wherein the one inlet stream receives an inlet flow; wherein the one outlet swing stream provides a variable outlet flow which varies with the inlet flow; wherein each outlet non-swing stream provides an invariant outlet flow which is invariant to changes in the inlet flow; wherein a first gain for the model of the splitter is a change in the variable outlet flow of the one outlet swing stream divided by a change in the inlet flow, wherein the first gain is set to one; and wherein a second gain for the model of the splitter equals a change in the invariant outlet flow of the at least one outlet non-swing stream divided by the change in the inlet flow, wherein the second gain is set to zero
Claims 4 and 12
Regarding claims 4 and 12, the combination of the cited prior arts does not describe:
wherein the plurality of models includes a model of a selector configured to receive one inlet stream, and configured to output one outlet diversion stream and at least one outlet non-diversion stream; wherein the one inlet stream receives an inlet flow; wherein the one outlet diversion stream provides a variable outlet flow which varies with the inlet flow; wherein each outlet non-diversion stream provides no material outlet flow; wherein a first gain for the model of the selector is a change in the variable outlet flow of the one outlet diversion stream divided by a change in the inlet flow, wherein the first gain is set to one; and wherein a second gain for the model of the selector equals a change in the outlet flow of the at least one outlet non-diversion stream divided by the change in the inlet flow, wherein the second gain is set to zero
Conclusion
The prior art made of record and not relied upon is considered pertinent to applicant’s disclosure.
US12656760 discloses a method for visually representing temporally aggregated measurement values includes generating image information over a period of time from temporally aggregated measurement values of a measurement variable associated with a technical object of a technical plant by an operator station server of a control system of the technical plant, adding information to the image information concerning fuzziness of the temporal aggregation of a specific temporally aggregated measurement value by comparison with the non-aggregated measurement values taken into consideration for the temporal aggregation of the specific measurement value, transmitting the image information to an operator station client, visually presenting the time profile of the temporally aggregated measurement values and the information concerning the fuzziness of the specific temporal aggregation of the temporally aggregated measurement points to an operator of the technical plant.
US7421374 discloses a method includes identifying a signal and a disturbance associated with a model. The signal and disturbance are identified using historical data associated with one or more process variables. The method also includes decomposing the signal and the disturbance at a plurality of resolution levels. The method further includes extracting a plurality of data segments from the signal using the decomposed signal and the decomposed disturbance. In addition, the method includes determining a quality of the model using the extracted data segments and at least a portion of the historical data.
US7743606 discloses a catalyst system that may regenerate while removing pollutants from an exhaust gas of an engine. The system may have a converter with multiple segments of chambers. At least one of the chambers may be regenerated while the remaining chambers are removing pollutants from the exhaust. The chambers may be rotated in turn for one-at-a-time regeneration. More than one chamber may be regenerated at a time to remove collected pollutants. The system may have plumbing and valves, and possibly mechanical movement of the chambers, within the system to effect the changing of a chamber for regeneration. The chambers connected to the exhaust may be in series or parallel. A particulate matter filter may be connected to the system, and it also may be regenerated to remove collected matter.
US7363200 discloses a matrix includes samples associated with a first signal and samples associated with a second signal. The second signal includes a first portion associated with the first signal and a second portion associated with at least one disturbance, such as white noise or colored noise. A projection of the matrix is produced using canonical QR-decomposition. Canonical QR-decomposition of the matrix produces an orthogonal matrix and an upper triangular matrix, where each value in the diagonal of the upper triangular matrix is greater than or equal to zero. The projection at least substantially separates the first portion of the second signal from the second portion of the second signal.
Any inquiry concerning this communication or earlier communications from the examiner should be directed to JASON LIN whose telephone number is (571)270-3175. The examiner can normally be reached on Monday-Friday 9:30 a.m. – 6:00 p.m. PST.
Examiner interviews are available via telephone, in-person, and video conferencing using a USPTO supplied web-based collaboration tool. To schedule an interview, applicant is encouraged to use the USPTO Automated Interview Request (AIR) at http://www.uspto.gov/interviewpractice.
If attempts to reach the examiner by telephone are unsuccessful, the examiner’s supervisor, Robert E. Fennema can be reached on (571)272-2748. The fax phone number for the organization where this application or proceeding is assigned is 571-273-8300.
Information regarding the status of an application may be obtained from the Patent Application Information Retrieval (PAIR) system. Status information for published applications may be obtained from either Private PAIR or Public PAIR. Status information for unpublished applications is available through Private PAIR only. For more information about the PAIR system, see http://pair-direct.uspto.gov. Should you have questions on access to the Private PAIR system, contact the Electronic Business Center (EBC) at 866-217-9197 (toll-free). If you would like assistance from a USPTO Customer Service Representative or access to the automated information system, call 800-786-9199 (IN USA OR CANADA) or 571-272-1000.
/JASON LIN/
Primary Examiner, Art Unit 2117