Notice of Pre-AIA or AIA Status
The present application, filed on or after March 16, 2013, is being examined under the first inventor to file provisions of the AIA .
Priority
The instant application is a 371 national stage entry to PCT/JP2021/022883, filed June 16, 2021, which properly claims priority to Provisional App. No 63/069,169 filed on August 24, 2020, and a copy of said foreign priority document was placed in the filed wrapper on January 30, 2023 and thus the effective filing date of the instance application’s claims is August 24, 2020.
Information Disclosure Statement
The information disclosure statement (IDS) was submitted on January 30, 2023. The submission is in compliance with the provisions of 37 CFR 1.97. Accordingly, the information disclosure statement is being considered by the Examiner.
Response to Amendment
In response to Applicant amendments, dated April 8, 2026, Examiner maintains the grounds of rejection under 35 U.S.C. 103.
Response to Arguments
Applicant’s arguments, filed April 8, 2026, regarding the rejections under 35 US.C. 103, have been considered but are not persuasive. Applicant states, on Page 8, that McGuffie does not cure the deficiencies of Ready-Campbell. However, McGuffie determines a duration of a task, as well as an average speed of that task (Paragraph [0027], “The server 16 may be configured to store this information and use it for future use and/or for management tasks such as productivity optimisation. The server 16 may be configured (eg programmed) to record operational information at the macro level (eg time taken or amount of paint used, or average travel speed when marking a particular football pitch or set of pitches)”). A duration is measured at an end of a task time, while an average speed of the task is measured by measuring the speed during that time window. Thus, a speed begins to be measured before a duration, and the timings are of a different nature. The remaining arguments are essentially the same as those addressed above and/or below and are unpersuasive and/or moot for at least the same reasons.
Claim Rejections - 35 USC § 103
The following is a quotation of 35 U.S.C. 103 which forms the basis for all obviousness rejections set forth in this Office action:
A patent for a claimed invention may not be obtained, notwithstanding that the claimed invention is not identically disclosed as set forth in section 102, if the differences between the claimed invention and the prior art are such that the claimed invention as a whole would have been obvious before the effective filing date of the claimed invention to a person having ordinary skill in the art to which the claimed invention pertains. Patentability shall not be negated by the manner in which the invention was made.
The text of those sections of Title 35, U.S. Code not included in this action can be found in a prior Office action.
The factual inquiries for establishing a background for determining obviousness under 35 U.S.C. 103 are summarized as follows:
1. Determining the scope and contents of the prior art.
2. Ascertaining the differences between the prior art and the claims at issue.
3. Resolving the level of ordinary skill in the pertinent art.
4. Considering objective evidence present in the application indicating obviousness or nonobviousness.
Claims 1-7, 11-13, and 16 are rejected under 35 U.S.C. 103 as being obvious over Ready-Campbell (US 20210149391 A1), previously of record, further in view of McGuffie (US 20190282889 A1), previously of record, herein after referred to simply as Ready-Campbell and McGuffie respectively.
Regarding Claim 1,
Ready-Campbell discloses the following limitations,
An operation control method for controlling an operation of a plurality of construction machines that perform excavation while moving, (Abstract, “This description provides an autonomous or semi-autonomous earth shaping vehicle that is capable of cooperatively hauling earth from a first location to a second location in a dig site with other earth shaping vehicles.”)
the method comprising: determining … a moving speed of the first construction machine during the excavation and an excavation time of the first construction machine to perform the excavation; (Paragraph [0181], “Based on the volume of earth to be excavated from the dig site, the volume of the excavation tool coupled to the excavation vehicle, or a combination thereof, the operation adjustment engine 950 determines an amount of time—an excavation time—for the excavation vehicle to excavate the volume of earth. Additionally, given the distance between the loading location and the dig location and the maximum velocity of the excavation vehicle, the operation adjustment engine 950 determines an amount of time—a navigation time—for the excavation vehicle to navigate from the dig location to the loading location. “ - time intervals for vehicle operation are determined. The time interval is integrally linked to a tool speed, Paragraph [0126], “In moving the tool through the target tool path, the hydraulic distribution engine 630 measures the speed of the tool and compares it to a target speed. The target speed refers to the speed that the drive system 210 is traveling.” And Paragraph [0146], “Alternatively, if a vehicle is taking less time to complete a fill routine, the hauling engine 820 may increase the speed of each vehicle traveling to conclude the earth shaping routine more efficiently.”)
and setting a moving speed and an excavation time of a second construction machine for excavation by the second construction machine after the excavation by the first construction machine is completed, wherein the setting is based on the moving speed and the excavation time of the first construction machine, (Paragraph [0141], “For example, in one embodiment an excavator may operate in coordination with other excavators, but, in another embodiment, the excavator may operate in coordination with one or more hauling vehicles” – multiple excavation vehicles can be used in one dig site. Paragraph [0213], “Alternatively, the traffic management engine 1050 detects the second earth shaping vehicle 115 closing with the threshold distance of the first vehicle 115 and generates instructions to decrease the velocity of the second vehicle to increase distance from the second vehicle to remove the second vehicle from the detection radius of the first vehicle.” The velocity of the vehicles is modified based on one another, to ensure routine spacing and prevent bottlenecks or collisions, Paragraph [0003], “However, in implementations in which several autonomous or semi-autonomous vehicles simultaneously perform different tasks, there exists a need for mechanisms for track the positions of each vehicle relative to other vehicles and to update each vehicle's control instructions to prevent collisions or bottlenecks in the simultaneous execution of the various earth moving tasks.”)
wherein the first construction machine and the second construction machine are of a same type (Paragraph [0141], “The multiple earth shaping vehicles may be configured with the same type or different earth shaping tools or specifications.” – the earth shaping vehicles of note may be either matching excavation vehicles or matching hauling vehicles, and further, both of these features may be combined, thus, in a set of self-loading haulers, Paragraph [0170], “In some embodiments, a hauling vehicle, for example hauling vehicles 912, may be capable of independently excavating earth from a dig location and loading the excavated earth into a hauling tool coupled to the vehicle. In such implementations, the hauling vehicle is configured with an excavation tool and a hauling tool. Examples of such self-loading hauling vehicles include, but are not limited to, a wheel tractor-scraper or an alternative scraper vehicle.” The circulation of a number of self-loading hauling vehicles, at a routine pace, where the vehicle timing and speed is relatively matched, is thus one embodiment of Ready-Campbell.)
However, Ready-Campbell does not disclose the following limitation,
Determining after excavation by a first construction machine is completed, a moving speed … and an excavation time
wherein a timing at which the moving speed is of the first construction machine is detected is different from a timing at which the excavation time of the first construction measure is measured.
However, this is taught by McGuffie, which uploads information about a task after its completion, including a duration and an average speed (Paragraph [0027], “The server 16 may be configured to store this information and use it for future use and/or for management tasks such as productivity optimisation. The server 16 may be configured (eg programmed) to record operational information at the macro level (eg time taken or amount of paint used, or average travel speed when marking a particular football pitch or set of pitches)”). A duration is measured at an end of a task time, while an average speed of the task is measured by measuring the speed during that time window. Thus, a speed begins to be measured before a duration, and the timings are of a different nature.
It would have been obvious to one of ordinary skill in the art, before the effective filing date, to have modified the vehicle coordination of Ready-Campbell with the discretely timed sharing of information as taught by McGuffie, as this is a means of enabling the optimization of tasks (Paragraph [0027], “The server 16 may be configured to store this information and use it for future use and/or for management tasks such as productivity optimisation.”). Furthermore, the combination is a simple substitution of elements yielding results which are predictable to one of ordinary skill in the art.
Regarding Claim 2,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
wherein: the first construction machine includes a scraper that performs the excavation, the second excavation machine includes a second scraper that performs the excavation, (Paragraph [0040], “Examples of hauling vehicles 115 b within the scope of this description include on-road or off-road trucks, for example dump trucks, articulated dump trucks or belly dumps, self-loading trucks, for example scrapers, scraper-tractors, high-speed dozers, or other wheeled or tracked equipment configured to tow a scraper attachment.” – the hauling and excavation vehicles may be integrated in the example of self-loading trucks, like a scraper-tractor, which uses a scraper to fill a towed bowl.)
and an amount by which the first scraper digs into a ground surface and an amount by which the second scraper digs into the ground surface are controlled to be the same (Paragraph [0082], “The volume check engine 440 measures the amount of earth in a tool 175 of an earth shaping vehicle 115, for example an excavation tool coupled to an excavation vehicle or a hauling tool coupled to a hauling vehicle, and makes a determination regarding whether or not the earth shaping vehicle should release the contents of the tool or continue executing an earth shaping routine.” – when both excavation vehicles are of a same type, the vehicles have equal fill thresholds and thus dig a same amount, and are also controlled to handle equivalent soil through equivalent digging configurations.)
Regarding Claim 3,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
comprising a moving processing of moving from an excavated area where the excavation is performed to a scattered area where an excavated object obtained by the excavation method is scattered (Paragraph [0039], “The hauling vehicle 115 b transports to earth from a first location in the dig site to a second location, for example a fill location.” – the fill location is a scattered area and a dig site is an excavated area).
wherein a moving time of the first construction machine to perform the machine to perform the moving process and a moving time of the second construction machine to perform the moving process are set to be the same. (Paragraph [0145], “To prevent traffic bottlenecks or collisions at points along the target tool path or the entrance to the fill location, the hauling engine 820 continuously tracks the location of each hauling vehicle relative to each other hauling vehicle 115 c of the fleet. If the hauling engine 820 detects that a first vehicle 115 c is about to or may eventually encounter or collide with a second vehicle 115 c because the first vehicle is moving too fast, the hauling engine 820 generates instructions to reduce the speed of the first vehicle.” – the timing of the hauling process is controlled for a dependable interval that prevents bottlenecks)
Regarding Claim 4,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 3. Ready-Campbell further discloses the following limitations,
wherein a moving speed of the first construction machine in the moving process and a moving speed of the second construction machine in the moving process are set to be the same (Paragraph [0145], “To prevent traffic bottlenecks or collisions at points along the target tool path or the entrance to the fill location, the hauling engine 820 continuously tracks the location of each hauling vehicle relative to each other hauling vehicle 115 c of the fleet. If the hauling engine 820 detects that a first vehicle 115 c is about to or may eventually encounter or collide with a second vehicle 115 c because the first vehicle is moving too fast, the hauling engine 820 generates instructions to reduce the speed of the first vehicle.” – the timing is controlling by modulating travel speeds which are too fast or too slow, to ensure a consistency and a same speed)
Regarding Claim 5,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
a moving process of moving from an excavated area where the excavation is performed to a scattered area where an excavated object obtained by the excavation is scattered; a discharging process of discharging the excavated object at the scattered area; and a redirection process of redirection from the scattered area to excavated area (Paragraph [0158], “In some implementations in which the excavation vehicle 904 takes multiple passes between the dig location 906 and the loading location 916 to excavate the specified amount of earth, the hauling vehicle 912 a remains at the loading location 916 until the full amount of earth has been transferred.” – the excavation material performs a digging, discharges the dirt at a scattered area 908, and returns to the excavated area 906 via a redirection process 910. See Figure 9A.)
wherein the second construction machine is controlled such that a time required for each of the moving process, the discharging process, and the redirection process of the first construction machine is equal to time required for each of the moving process, the discharging process, and the redirection process of the second construction machine (Paragraph [0213], “Alternatively, the traffic management engine 1050 detects the second earth shaping vehicle 115 closing with the threshold distance of the first vehicle 115 and generates instructions to decrease the velocity of the second vehicle to increase distance from the second vehicle to remove the second vehicle from the detection radius of the first vehicle.” The velocity of the vehicles is modified based on one another, to ensure routine spacing and prevent bottlenecks or collisions, Paragraph [0003], “However, in implementations in which several autonomous or semi-autonomous vehicles simultaneously perform different tasks, there exists a need for mechanisms for track the positions of each vehicle relative to other vehicles and to update each vehicle's control instructions to prevent collisions or bottlenecks in the simultaneous execution of the various earth moving tasks.” A speed and time interval are integrally linked, Paragraph [0146], “Alternatively, if a vehicle is taking less time to complete a fill routine, the hauling engine 820 may increase the speed of each vehicle traveling to conclude the earth shaping routine more efficiently.”)
Regarding Claim 6,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 5. Ready-Campbell further discloses the following limitations,
wherein the moving speed of the second construction machine is controlled such that the moving speed of the first machine, the discharging speed, and the redirection process is equal to the moving speed of the second construction machine in each of the moving process, the discharging process, and the redirection process (Paragraph [0213], “Alternatively, the traffic management engine 1050 detects the second earth shaping vehicle 115 closing with the threshold distance of the first vehicle 115 and generates instructions to decrease the velocity of the second vehicle to increase distance from the second vehicle to remove the second vehicle from the detection radius of the first vehicle.” The velocity of the vehicles is modified based on one another, to ensure routine spacing and prevent bottlenecks or collisions, Paragraph [0003], “However, in implementations in which several autonomous or semi-autonomous vehicles simultaneously perform different tasks, there exists a need for mechanisms for track the positions of each vehicle relative to other vehicles and to update each vehicle's control instructions to prevent collisions or bottlenecks in the simultaneous execution of the various earth moving tasks.” A speed and time interval are integrally linked, Paragraph [0146], “Alternatively, if a vehicle is taking less time to complete a fill routine, the hauling engine 820 may increase the speed of each vehicle traveling to conclude the earth shaping routine more efficiently.”)
Regarding Claim 7,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
wherein the operation of the second construction machine is controlled in an unmanned manner (Abstract, “This description provides an autonomous or semi-autonomous earth shaping vehicle that is capable of cooperatively hauling earth from a first location to a second location in a dig site with other earth shaping vehicles.”)
Regarding Claim 11,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
obtaining data directed to a drive of the first construction machine at a first yard, wherein the data is applied at a second yard that is different from the first yard (Paragraph [0126], “Often, greater than expected soil friction is due to the tool being too deep (or angled along a path proceeding downward), thus generating more friction and often causing the tool to fall off the target tool path. To compensate, the hydraulic distribution engine 740 may adjust the tool to a shallower depth or angle, which will accomplish reducing the soil friction and raising tool speed. This process may play out in reverse for a tool speed greater than expected, which may be adjusted by lowering the tool or setting it at a deeper angle.” – dynamic feedback is used along a tool path, thus, a first yard of performance informs the operation at a next yard).
Regarding Claim 12,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
wherein the excavation by the first construction machine starts in accordance with an end of the excavation by a last construction machine of a plurality of construction machines that includes the first construction machine and the second construction machine (Paragraph [0199], “As a result, the hauling engine 820 is responsible for monitoring the dynamic position of each hauling vehicle 912 both in the coordinate space of the dig site and relative to other hauling vehicles (or other earth shaping vehicles) in the dig site and adjust the navigation and instructions of each vehicle to prevent collisions or traffic buildups between the start location and end location.” – one vehicle may go after another, after another, and so on)
Regarding Claim 13,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. Ready-Campbell further discloses the following limitations,
wherein the first construction machine performs an excavation process for carrying out the excavation, a transportation process to transport excavated material from the excavation process to a discharge location, a discharge process to discharge the excavated material at the discharge location, and a redirection process to move an excavation site is completed. (Figure 9a, elements 906, excavation in an excavation area, travelling via transportation process 918 to a discharge area 916 or equivalently a discharge area 908, and element 910, for returning in a redirection process. See further, Paragraph [0170], “Examples of such self-loading hauling vehicles include, … a wheel tractor-scraper… As the excavation tool excavates earth, the operation adjustment module engine 950 instructs the excavation tool to transfer earth into a hauling tool coupled to the hauling vehicle … a hauling vehicle may navigate directly to the dig location to execute instructions for a digging routine and, subsequently, executing a hauling routine to haul earth to a fill location.”)
Regarding Claim 16,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. McGuffie further already teaches the following limitations,
wherein detection of the moving speed of the first construction machine is initiated prior to initiation of measuring the excavation time of the first construction machine. (Paragraph [0027], “The server 16 may be configured to store this information and use it for future use and/or for management tasks such as productivity optimisation. The server 16 may be configured (eg programmed) to record operational information at the macro level (eg time taken or amount of paint used, or average travel speed when marking a particular football pitch or set of pitches)”). A duration is measured at an end of a task time, while an average speed of the task is measured by measuring the speed during that time window. Thus, a speed begins to be measured before a duration, and the timings are of a different nature.)
Claims 8-10 are rejected under 35 U.S.C. 103 as being unpatentable over Ready-Campbell as applied to Claim 1 above, in view of Li (WO 2019189888 A1), previously of record, herein after referred to simply as Li.
Regarding Claim 8,
The combination of Ready-Campbell and McGuffie, as shown, teaches all the limitations of Claim 1. However, Ready-Campbell does not disclose the following limitations,
obtaining data directed to a drive of the first construction machine; and applying the data to the excavation on a following day and subsequent days.
However, Li, in the same field of endeavor, teaches such an application of data (Paragraph [0101], Lines 1-8, “The simulator unit 3102D can perform an operation simulation included in the work pattern of the excavator 100 based on input conditions such as an input environmental condition, work condition, and work pattern for each type. Thereby, the simulator unit 3102 can generate a work pattern. Therefore, the reinforcement learning unit 3102C performs not only reinforcement learning based on past work patterns (work pattern performance information) acquired by the information acquisition unit 3101 but also reinforcement based on information on new work patterns generated by the simulator unit 3102D.” – past work informs future work, which include work on another day and thereafter. The environmental information includes weather, Paragraph [0065], Lines 7-8, “The environmental condition performance information may include weather information.”)
It would have been obvious to one of ordinary skill in the art before the effective filing date of the claimed invention, with a reasonable likelihood of success, to have modified the vehicle collaboration of Ready-Campbell with the learning process of Li, as this optimizes vehicle work (Paragraph 5, Lines 1-5, “However, in the method using the actual work data with high work quality among the past actual data, it is not possible to output the support data whose evaluation regarding a certain target index (for example, the speed of work) exceeds the past actual result. Therefore, there is room for improvement in terms of optimizing (maximizing) the evaluation related to the target index.”). Further, the combination is a simple substitution of elements yielding results which are predictable to one of ordinary skill in the art.
Regarding Claim 9,
The combination of Ready-Campbell, McGuffie, and Li, as shown, teaches all the limitations of Claim 8. Li further already teaches the following limitation,
correcting the data with an environmental condition (Paragraph [0101], Lines 1-3, “The simulator unit 3102D can perform an operation simulation included in the work pattern of the excavator 100 based on input conditions such as an input environmental condition,”)
Regarding Claim 10,
The combination of Ready-Campbell, McGuffie, and Li, as shown, teaches all the limitations of Claim 8. Li further already teaches the following limitation,
wherein the environmental condition includes weather (Paragraph [0065], Lines 7-8, “The environmental condition performance information may include weather information.”)
Claims 14-15 are rejected under 35 U.S.C. 103 as being unpatentable over the combination of Ready-Campbell and McGuffie as applied to Claim 13 above in view of official notice.
Regarding Claim 14,
The combination of Ready Campbell and McGuffie, as shown, teaches all the limitations of Claim 13. However, Ready-Campbell does not disclose the following limitations,
wherein the first construction machine moves continuously from the excavation process to the redirection process without stopping.
However, Examiner takes official notice that a vehicle dumping may proceed without stopping. It would have been obvious to one of ordinary skill in the art, before the effective filing date of the claimed invention, to have modified Ready-Campbell with a continuous work process, as this allows for less starting and stopping, increasing a time efficiency and potentially reducing wear and tear upon a construction machine.
Regarding Claim 15,
The combination of Ready Campbell, McGuffie, and official notice, as shown, teaches all the limitations of Claim 14. Ready-Campbell further discloses the following limitations,
detecting a time for the first construction machine to perform each of the transportation process, the discharge process, and the redirection process and a movement speed of the first construction machine during each of the transportation process, the discharge process, and the redirection process (Paragraph [0181], “Based on the volume of earth to be excavated from the dig site, the volume of the excavation tool coupled to the excavation vehicle, or a combination thereof, the operation adjustment engine 950 determines an amount of time—an excavation time—for the excavation vehicle to excavate the volume of earth. Additionally, given the distance between the loading location and the dig location and the maximum velocity of the excavation vehicle, the operation adjustment engine 950 determines an amount of time—a navigation time—for the excavation vehicle to navigate from the dig location to the loading location. “ - time intervals for vehicle operation are determined. A navigation time, during multiple passes, includes afterwards a redirection process, discharging process, and accordant time intervals, as the whole of the vehicle path is planned and measured. The time interval is integrally linked to a tool speed, Paragraph [0126], “In moving the tool through the target tool path, the hydraulic distribution engine 630 measures the speed of the tool and compares it to a target speed. The target speed refers to the speed that the drive system 210 is traveling.” And Paragraph [0146], “Alternatively, if a vehicle is taking less time to complete a fill routine, the hauling engine 820 may increase the speed of each vehicle traveling to conclude the earth shaping routine more efficiently.”)
applying the moving speed, the excavation time, the time for the first construction machine to perform each of the transportation process, the discharge process, and the redirection process, and the movement speed of the first construction machine during each of the transportation process, the discharge process, and the redirection process to control of the second construction machine (Paragraph [0213], “Alternatively, the traffic management engine 1050 detects the second earth shaping vehicle 115 closing with the threshold distance of the first vehicle 115 and generates instructions to decrease the velocity of the second vehicle ..” The velocity of the vehicles is modified based on one another, to ensure routine spacing and prevent bottlenecks or collisions, Paragraph [0003], “However, in implementations in which several autonomous or semi-autonomous vehicles simultaneously perform different tasks, there exists a need for mechanisms for track the positions of each vehicle relative to other vehicles and to update each vehicle's control instructions to prevent collisions or bottlenecks in the simultaneous execution of the various earth moving tasks.” A speed and time interval are integrally linked, Paragraph [0146], “… if a vehicle is taking less time to complete a fill routine, the hauling engine 820 may increase the speed of each vehicle traveling…”)
Conclusion
The prior art made of record and not relied upon is considered pertinent to applicant's disclosure. Atkinson (US 20200011034 A1), previously of record, teaches that two tractor-scrapers can perform collaborative tandem excavation including a relative speed control (Paragraph [0070]). Marsolek (US 20170205814 A1), previously of record, teaches a consistent pacing of material transportation by a fleet of vehicles (Paragraph [0111]). Liu (US 20210198866 A1), previously of record, teaches the simultaneous and coordinated operation of multiple excavators (Paragraph [0022]). Cella (US20190171187A1), previously of record, equivocates between earth-moving and other industrial systems as comprising similar coordination requirements (Paragraph [0223]).
Applicant's amendment necessitated the new ground(s) of rejection presented in this Office action. Accordingly, THIS ACTION IS MADE FINAL. See MPEP § 706.07(a). Applicant is reminded of the extension of time policy as set forth in 37 CFR 1.136(a).
A shortened statutory period for reply to this final action is set to expire THREE MONTHS from the mailing date of this action. In the event a first reply is filed within TWO MONTHS of the mailing date of this final action and the advisory action is not mailed until after the end of the THREE-MONTH shortened statutory period, then the shortened statutory period will expire on the date the advisory action is mailed, and any nonprovisional extension fee (37 CFR 1.17(a)) pursuant to 37 CFR 1.136(a) will be calculated from the mailing date of the advisory action. In no event, however, will the statutory period for reply expire later than SIX MONTHS from the mailing date of this final action.
Any inquiry concerning this communication or earlier communications from the examiner should be directed to KAREN LYNELLE FURGASON whose telephone number is (571)272-5619. The examiner can normally be reached Monday - Friday, 7:30 AM - 6 PM.
Examiner interviews are available via telephone, in-person, and video conferencing using a USPTO supplied web-based collaboration tool. To schedule an interview, applicant is encouraged to use the USPTO Automated Interview Request (AIR) at http://www.uspto.gov/interviewpractice.
If attempts to reach the examiner by telephone are unsuccessful, the examiner’s supervisor, Erin Bishop can be reached at 571-270-3713. The fax phone number for the organization where this application or proceeding is assigned is 571-273-8300.
Information regarding the status of published or unpublished applications may be obtained from Patent Center. Unpublished application information in Patent Center is available to registered users. To file and manage patent submissions in Patent Center, visit: https://patentcenter.uspto.gov. Visit https://www.uspto.gov/patents/apply/patent-center for more information about Patent Center and https://www.uspto.gov/patents/docx for information about filing in DOCX format. For additional questions, contact the Electronic Business Center (EBC) at 866-217-9197 (toll-free). If you would like assistance from a USPTO Customer Service Representative, call 800-786-9199 (IN USA OR CANADA) or 571-272-1000.
/K.L.F./ Examiner, Art Unit 3665
/Erin D Bishop/ Supervisory Patent Examiner, Art Unit 3665